Skip to content
General ConstructionNorth LawndalePermit issued

Temporary Event Structure at 1401 S Sacramento Dr, Chicago

1401 S SACRAMENTO DR, North Lawndale

Winston

Sinra's conciergeOnline now

Planning general construction work near North Lawndale? I’ll scope it, price it, and line up the right pro.

Reported project cost

$175,000

As declared on the permit filing.

Issued
August 31, 2026
Expires
—
License
—

What was permitted

Residents near North Lawndale can observe the substantial investment in temporary event infrastructure, with a permit for a large tent platform at 1401 S Sacramento Dr. This project, supporting Riot Fest 2026, involves erecting a significant tiered platform structure.

The estimated project cost for this temporary setup is $175,000, with a permit issued on August 31, 2026, and construction scheduled from September 8th to September 24th, 2026. BIG TENT EVENTS is the contractor for this large-scale event build.

Plan a similar project

Want work like this done at your place?

Tell us what you have in mind. We scope it, price it against work like this in North Lawndale, and lines up the right contractor. You approve; we handle the back-and-forth.

View the official permit record

Tracking number, work description, cost and dates

Tracking number101087373
Work permit #—
Job filing number—
Work type—
StatusACTIVE
Job descriptionPERMIT EXPIRES ON 10/31/2026 ERECTION STARTS: 9/8/2026, ERECTION ENDS: 9/24/2026. RIOT FEST 2026- TENT PLATFORMTENT PLATFORM- PEER REVIEW- 3 DAY EVENT (9/18-20/2026)ERECT ONE (1) 150X50 RING LOCK TIERED PLATFORM WITH ONE (1) 30X150 (9MX45M) STRUCTURE.SETUP 9/8/2026 - REMOVE 9/24/2026ASSEMBLY
Floor / unit—
Estimated cost$175,000
ApprovedAugust 18, 2026
IssuedAugust 31, 2026
Expires—