Skip to content
ElectricalOuter MissionPermit issued

EV Charging Station Installation at 2201V Alemany Bl, San Francisco

2201V Alemany Bl, Outer Mission, 94112

Winston

Sinra's conciergeOnline now

Planning electrical work near Outer Mission? I’ll scope it, price it, and line up the right pro.

Reported project cost

$2,140,000

As declared on the permit filing. Alterations · Prkng Garage/Public.

Issued
August 31, 2026
Expires
—
License
—

What was permitted

For those in the Outer Mission neighborhood interested in large-scale EV infrastructure, this permit details a significant project. It involves demolition, grading, and the installation of multiple EV chargers, transformers, and associated equipment.

This project was issued on August 31, 2026, with a substantial estimated cost of $2,140,000. Five Engineering & Plumbing Inc was the contractor for this extensive electrical and site work.

Plan a similar project

Want work like this done at your place?

Tell us what you have in mind. We scope it, price it against work like this in Outer Mission, and lines up the right contractor. You approve; we handle the back-and-forth.

View the official permit record

Tracking number, work description, cost and dates

Tracking number202607245524
Work permit #—
Job filing number—
Work typeAlterations · Prkng Garage/Public
Statusissued
Job descriptiondemolition of existing surfaces for the installation of ev charging station. grading of surfaces associated with evse to comply with ada requirement. install 1 utility transformer, 1 switchboard assembly, 8 400kw alpitronic hyc400 ev charges, 16 ev sign posts, 26 bollards, 1 ornamental fence.
Floor / unit—
Estimated cost$2,140,000
ApprovedAugust 31, 2026
IssuedAugust 31, 2026
Expires—
BBL—
BIN—

Related searches

EV charging stationelectric vehicle infrastructuretransformerOuter MissionSan FranciscoPrkng Garage/Public$2M+