Skip to content
General ConstructionPermit issued

EV Charger and Canopy Installation at 2211 S IH 35 SVRD NB

2211 S IH 35 SVRD NB, 78741

Winston

Sinra's conciergeOnline now

Planning general construction work in Austin? I’ll scope it, price it, and line up the right pro.

Reported project cost

Not reported

The filer did not disclose a cost on this permit. Building Permit · Remodel.

Issued
October 9, 2026
Expires
April 8, 2027
License
General Contractor

What was permitted

This project involves preparing existing surfaces for the installation of electric vehicle (EV) chargers and a lit canopy at 2211 S IH 35 SVRD NB in Austin. The work also includes grading to ensure ADA compliance for the EV charging stations.

The permit was issued on October 9, 2026, and includes the installation of a utility transformer and switchboard assembly, along with four 400KW EV chargers. Bear Utilities, LLC is the general contractor for this upgrade.

Plan a similar project

Want work like this done at your place?

Tell us what you have in mind. We scope it, price it against work like this, and lines up the right contractor. You approve; we handle the back-and-forth.

View the official permit record

Tracking number, work description, cost and dates

Tracking number2025-158719 BP
Work permit #—
Job filing number—
Work typeBuilding Permit · Remodel
StatusActive
Job descriptionDemolition of existing surfaces for the installation of EV chargers and lit canopy. Grading of surfaces associated with EVSE to comply with ADA requirements. Install (1) utility transformer Install (1) switchboard assembly. Install (4) 400KW ALPITRONIC HYC400 EV chargers. Install (7) EV sign posts. Install (1) accessible EV sign posts.
Floor / unit—
Estimated costNot reported
ApprovedOctober 9, 2025
IssuedOctober 9, 2026
ExpiresApril 8, 2027
BBL—