14021 MATTEROD DR, 78617
Homeowners in Austin can see the investment involved in adding solar power to their property. This permit covers a 7.38kW solar system with 18 QCell panels and a 10C battery, designed to enhance home energy independence.
This electrical permit was issued on July 31, 2026, and is currently active. The reported project cost for this solar installation is $67,384, handled by contractor Greenstar Power.
A significant investment of $67,384 was made for a 7.38kW solar system with battery backup at 14021 Matterod Dr, offering a glimpse into the cost of renewable energy upgrades in the area.
Issued
July 31, 2026
Expires
January 27, 2027
License
Electrical Contractor
See what a project like this costs near you
We'll compare your scope against real permits and licensed contractors in the area.
Start my estimate →Free · takes 60 seconds · no account needed
Filed by Greenstar Power
View the official permit record
Tracking number, work description, cost, and dates
| Tracking Number | 2026-091191 EP |
| Work Permit # | — |
| Job Filing Number | — |
| Work Type | Electrical Permit · Auxiliary Power |
| Status | Active |
| Job Description | SOLAR INSTALLTION WITH A SYSTEAM SIZE OF 7.38kW SYSTEAM WITH (18) QCell410 on IQ8HC (1) 10C battery |
| Floor / Unit | — |
| Estimated Cost | $67,384 |
| Approved | July 15, 2026 |
| Issued | July 31, 2026 |
| Expires |
| January 27, 2027 |
| BBL | — |
| BIN | — |