Skip to content
General ConstructionBronxPermit issued

General Construction at 100 East 182 Street, Fordham Heights

100 EAST 182 STREET, Bronx, 10453 · Fordham Heights

Winston

Sinra's conciergeOnline now

Planning general construction work near Fordham Heights? I’ll scope it, price it, and line up the right pro.

Reported project cost

$60,000

As declared on the permit filing. General Construction.

Issued
April 6, 2026
Expires
May 29, 2026
License
General Contractor

What was permitted

This project involves alteration work, including repointing the parapet along Morris Avenue and East 182nd Street at 100 East 182 Street in Fordham Heights. The project also includes installing safety guard rails and replacing window lintels.

The permit was issued on April 6, 2026, with a cost of $60,000. ROSE CONTRACTOR NY, INC (GC) is the contractor for this general construction project.

Plan a similar project

Want work like this done at your place?

Tell us what you have in mind. We scope it, price it against work like this in Bronx, and lines up the right contractor. You approve; we handle the back-and-forth.

View the official permit record

Tracking number, work description, cost and dates

Tracking number594681167
Work permit #X01028203-I1-GC
Job filing number—
Work typeGeneral Construction
StatusPermit Issued
Job descriptionAlteration type 2 Directive 14 to repoint parapet along Morris Avenue and East 182nd Street. Install safety guard rails along side yard. Change 8 existing steel window lintels on top floor windows. No change in occupancy use or egress.
Floor / unitRoof
Estimated cost$60,000
ApprovedOctober 28, 2025
IssuedApril 6, 2026
ExpiresMay 29, 2026
BBL—
BIN—

Property owner

Walton Heights Hdfc

Gerard Wollweber