What was permitted
This permit is for the construction of a new unmanned electrical vehicle charging station in the University Heights neighborhood of the Bronx. The project involves the installation of essential components like an equipment enclosure, switch assembly, and multiple charging dispensers.
Issued on October 20, 2026, this general construction project has an estimated cost of $730,000. POWERONE ELECTRICAL CONTR is the General Contractor responsible for this significant infrastructure development.
Plan a similar project
Want work like this done at your place?
Tell us what you have in mind. We scope it, price it against work like this in Bronx, and lines up the right contractor. You approve; we handle the back-and-forth.
View the official permit record
Tracking number, work description, cost and dates
View the official permit record
Tracking number, work description, cost and dates
| Tracking number | 633899918 |
|---|---|
| Work permit # | X01207536-I1-GC |
| Job filing number | — |
| Work type | General Construction |
| Status | Permit Issued |
| Job description | Jerome - New York Power Authority proposes to construct an unmanned electrical vehicle charging station which will include. 1 equipment enclosure, 1 switch assembly, 3 BTC power Gen IV power units, 6 BTC power gen IV charging dispensers |
| Floor / unit | Floor Number(s) 1, Floor Number(s) 2, Floor Number(s) 3, Floor Number(s) 4, Floor Number(s) 5, Floor Number(s) 6 |
| Estimated cost | $730,000 |
| Approved | June 16, 2025 |
| Issued | October 20, 2026 |
| Expires | June 27, 2027 |
| BBL | — |
| BIN | — |
Property owner
Piso
Connor Lyons