What was permitted
For property owners in Tribeca-Civic Center, this permit details the costs associated with structural work within an elevator shaft. The project involves installing new wood framing and subflooring at each level of the shaft, following previous abandonment of elevator equipment.
This general construction permit was issued on June 4, 2026, with an estimated project cost of $165,000. POLER CONSTRUCTION INC is the general contractor for this specialized structural work.
Plan a similar project
Want work like this done at your place?
Tell us what you have in mind. We scope it, price it against work like this in Manhattan, and lines up the right contractor. You approve; we handle the back-and-forth.
View the official permit record
Tracking number, work description, cost and dates
View the official permit record
Tracking number, work description, cost and dates
| Tracking number | 593359849 |
|---|---|
| Work permit # | M01297206-I1-GC-CX |
| Job filing number | — |
| Work type | General Construction |
| Status | Permit Issued |
| Job description | Install new wood framing and subflooring at each level of the interior elevator shaft. Elevator equipment was removed and the shaft abandoned by others on applications M00858075, and M01166935. |
| Floor / unit | Floor Number(s) 1 through 6, Roof |
| Estimated cost | $165,000 |
| Approved | February 9, 2026 |
| Issued | June 4, 2026 |
| Expires | September 17, 2026 |
| BBL | — |
| BIN | — |
Property owner
41 North Moore St Condo
Rich Craybas