What was permitted
Work is scheduled to commence at 45 Twin Pines Drive in Brooklyn's Spring Creek-Starrett City neighborhood, involving the removal of existing concrete sidewalks and asphalt driveways. The project includes the installation of new permeable pavers, bollards, and guardrails, along with reinstating existing lighting.
This permit was issued on September 9, 2026, with an estimated project cost of $74,220. KAMA CONSTRUCTION CORP (GC) is the contractor undertaking this exterior improvement project.
Plan a similar project
Want work like this done at your place?
Tell us what you have in mind. We scope it, price it against work like this in Brooklyn, and lines up the right contractor. You approve; we handle the back-and-forth.
View the official permit record
Tracking number, work description, cost and dates
View the official permit record
Tracking number, work description, cost and dates
| Tracking number | 550722171 |
|---|---|
| Work permit # | B01381046-I1-GC |
| Job filing number | — |
| Work type | General Construction |
| Status | Permit Issued |
| Job description | REMOVAL OF EXISTING CONCRETE SIDEWALK AND ASPHALT DRIVEWAY, INSTALLATION OF NEW CURB, REINSTALLEXISTING LIGHTING ON NEW CONCRETE FOOTING, INSTALL GUARDRAIL, PERMEABLE PAVERS, BOLLARDS. |
| Floor / unit | Open Space |
| Estimated cost | $74,220 |
| Approved | June 25, 2026 |
| Issued | September 9, 2026 |
| Expires | September 29, 2026 |
| BBL | — |
| BIN | — |