Reported project cost

$75,000

As declared on the permit filing. General Construction.

Issued
October 6, 2026
Expires
November 24, 2026
License
General Contractor

What was permitted

This general construction permit is for the installation of multiple Level 2 EV charging stations at a property on Zerega Avenue in the Castle Hill-Unionport neighborhood of the Bronx. The project also includes the installation of new main disconnects and breakers to support the electrical load.

Issued on October 6, 2026, the estimated project cost for this electrical infrastructure upgrade is $75,000. CNB CONTRACTING CORP is listed as the general contractor.

Plan a similar project

Want work like this done at your place?

Tell us what you have in mind. We scope it, price it against work like this in Bronx, and lines up the right contractor. You approve; we handle the back-and-forth.

View the official permit record

Tracking number, work description, cost and dates

Tracking number525744057
Work permit #X01452460-I1-GC
Job filing number—
Work typeGeneral Construction
StatusPermit Issued
Job descriptionINSTALLING (12) NEW DUAL PORT & (1) Single port LEVEL 2 EV CHARGING STATIONS (Autel AC Pro 80A 19.2kW. INSTALL (1) NEW SEB INSTALL (1) NEW 1600A 120/208V 3PH-4W MAIN DISCONNECT. INSTALL (2) NEW 800A 120/208V. INSTALL (25) 100A 2-POLE BREAKERS
Floor / unitOpen Space
Estimated cost$75,000
ApprovedOctober 1, 2026
IssuedOctober 6, 2026
ExpiresNovember 24, 2026
BBL—
BIN—

Property owner