General Construction at 900 Third Avenue, Manhattan
900 THIRD AVENUE, MANHATTAN, 10022 · East Midtown-Turtle Bay
What was permitted
A general construction project is underway at 900 Third Avenue in East Midtown-Turtle Bay. The work involves installing a rated wall, door, and platform in the cellar's Gas Meter Room.
The permit was issued on March 30, 2026, with an estimated cost of $45,000. The contractor for this project is PHASE 3 INTERIORS LLC.
Homeowners and property owners in East Midtown-Turtle Bay can see the $45,000 cost for this general construction project.
What it cost
Issued
March 30, 2026
Expires
September 30, 2026
License
General Contractor
Price your own project
See what a project like this costs near you
We'll compare your scope against real permits and licensed contractors in the area.
Start my estimate →Free · takes 60 seconds · no account needed
Filed by PHASE 3 INTERIORS LLC · 31 permits across 7 neighborhoods
View the official permit record
Tracking number, work description, cost, and dates
+
View the official permit record
Tracking number, work description, cost, and dates
| Tracking Number | 846356453 |
| Work Permit # | M01182658-I1-GC |
| Job Filing Number | — |
| Work Type | General Construction |
| Status | Permit Issued |
| Job Description | Installation of rated wall, door and platform in the cellar (Gas Meter Room) as per plans. No change to use, egress or occupancy. |
| Floor / Unit | Cellar |
| Estimated Cost | $45,000 |
| Approved | March 4, 2025 |
| Issued | March 30, 2026 |
| Expires | September 30, 2026 |
| BBL | — |
| BIN | — |
Property Owner
PARAMOUNT GROUP