Mechanical Systems Upgrade at 6 Metrotech, Brooklyn
6 METROTECH, BROOKLYN, 11201 · Downtown Brooklyn-DUMBO-Boerum Hill
What was permitted
Significant work on mechanical systems is underway at 6 Metrotech in the Downtown Brooklyn area, involving the removal of existing ducts and piping on the 5th floor and roof. This is to accommodate new mechanical equipment, impacting the building's HVAC infrastructure.
The permit for this extensive project was issued on June 23, 2026, with an estimated cost of $7,300,000. GILBANE BUILDING COMPANY is listed as the general contractor for this substantial mechanical upgrade.
Residents and businesses in Downtown Brooklyn should be aware of a major mechanical system overhaul at 6 Metrotech, representing a significant investment in building infrastructure.
What it cost
Issued
June 23, 2026
Expires
January 1, 2027
License
General Contractor
Price your own project
See what a project like this costs near you
We'll compare your scope against real permits and licensed contractors in the area.
Start my estimate →Free · takes 60 seconds · no account needed
Filed by GILBANE BUILDING COMPANY · 130 permits across 21 neighborhoods
View the official permit record
Tracking number, work description, cost, and dates
+
View the official permit record
Tracking number, work description, cost, and dates
| Tracking Number | 245730407 |
| Work Permit # | B01261648-S1-MS |
| Job Filing Number | — |
| Work Type | Mechanical Systems |
| Status | Permit Issued |
| Job Description | Removal of ducts and CHWS&R/HWS&R piping on the 5th floor, removal of AHU and associated ducts and piping on the Roof to accommodate new mechanical equipment on Roof and related ducts and piping on 5th Fl.. no change in use, egress or occupancy |
| Floor / Unit | Floor Number(s) 5 through 5, Roof |
| Estimated Cost | $7,300,000 |
| Approved | October 10, 2025 |
| Issued | June 23, 2026 |
| Expires | January 1, 2027 |
| BBL | — |
| BIN | — |
Property Owner
NEW YORK UNIVERSITY