Supported Scaffold Stair Tower at 142 Pierrepont Street, Brooklyn
142 PIERREPONT STREET, BROOKLYN, 11201 · Brooklyn Heights
What was permitted
A permit has been issued for the installation of a temporary system scaffold stair tower at 142 Pierrepont Street in the Brooklyn Heights neighborhood of Brooklyn. This type of installation is often used to provide safe access during construction or renovation.
This permit was issued on April 28, 2026, with an estimated cost of $1,000. The installation is temporary and does not affect the building's use, egress, or occupancy. Spring Scaffolding LLC is the contractor for this project.
In Brooklyn Heights, temporary scaffold stair towers, like the one permitted at 142 Pierrepont Street, are being installed for approximately $1,000.
What it cost
Issued
April 28, 2026
Expires
March 1, 2027
License
General Contractor
Price your own project
See what a project like this costs near you
We'll compare your scope against real permits and licensed contractors in the area.
Start my estimate →Free · takes 60 seconds · no account needed
Filed by SPRING SCAFFOLDING LLC · 446 permits across 62 neighborhoods
View the official permit record
Tracking number, work description, cost, and dates
+
View the official permit record
Tracking number, work description, cost, and dates
| Tracking Number | 243194764 |
| Work Permit # | B01383840-S1-SF |
| Job Filing Number | — |
| Work Type | Supported Scaffold |
| Status | Permit Issued |
| Job Description | INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD STAIR TOWER AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| Floor / Unit | Open Space |
| Estimated Cost | $1,000 |
| Approved | April 28, 2026 |
| Issued | April 28, 2026 |
| Expires | March 1, 2027 |
| BBL | — |
| BIN | — |
Property Owner
SAINT ANN'S SCHOOL